UETN Projects and Initiatives For FY2017

This initiatives list represents projects that will be addressed during fiscal year 2017 (Q1: July - Sept, Q2: Oct - Dec, Q3: Jan - March, Q4: April - June). This does not include ongoing operations or maintenance items.
Network Services Application Services Support Services Operations
Network Services

 1
IVC Refresh 2017

Lead: Technical Services
Deferred
85%

Last Update: 7/26/17
2
Coordinate Four Corners Network Development Project

Lead: Technical Services
Deferred
20%

Last Update: 7/26/17
3
Continue to identify and evaluate emerging synchronous video solutions based on the identified needs of the UETN stakeholder.

Lead: Technical Services
Ongoing

Last Update: 7/26/17
4
Continue IT Asset Management Project

Lead: Technical Services

Last Update: 4/12/17
5
Coordinate CIB funded structural improvements to Cold Springs Communication site (Abajo Mountains outside of Monticello)

Lead: Technical Services

Last Update: 1/10/17
6
Coordinate CIB funded tower replacement at Cedar Mesa (Just above Moki Dugway overlooking Bluff and Mexican Hat, UT).

Lead: Technical Services

Last Update: 7/26/17
7
Coordinate, engineer and install USHE alternate 10 gigabit broadband circuit from USHE Offices at Gateway to the Downtown Data Center.

Lead: Technical Services

Last Update: 4/12/17
8
Define, communicate and implement new UEN PoP requirements.

Lead: Technical Services
Deferred
92%

Last Update: 7/26/17
9
Continue Technical Services equipment replacement/refresh.

Lead: Technical Services
Ongoing

Last Update: 726/17
10
Complete transition to the new Joint Master Control.

Lead: K. Anderson

11
Address trend in audience access to media by exploring options for streaming video online.

Lead: K. Anderson
Ongoing

Last Update: 6/26/17
12
Continue to broadcast high-quality educational programming that aligns with stakeholder needs.

Lead: K. Anderson
Ongoing

Last Update: 6/26/17
13
Daggett County Fiber Project

Lead: Technical Services
Deferred
30%

Last Update: 7/26/17
14
Support the Salt Lake City School District Data Center move project.

Lead: Technical Services

Last Update: 7/26/17