UEN Projects and Initiatives For FY2015

This initiatives list represents projects that will be addressed during fiscal year 2015 (Q1: July - Sept, Q2: Oct - Dec, Q3: Jan - March, Q4: April - June). This does not include ongoing operations or maintenance items.
Network Services Application Services Support Services Operations
Network Services

Description Lead % Complete Status Report as of 7/1/2015
1 Continue to design and implement the move of 500 Tellabs circuits (move from Optera to Tellabs) K.Quire The conversion of Geomax circuits from the Optera optical transport to the new Tellabs (now Coriant) optical transport was completed on December 31st, 2014. Circuit moves are 100% complete.

Followup activities will include shutting down and physically removing the old Optera hardware from all UEN PoPs and District Offices around the state. UEN’s Erate and Accounting teams are working with CenturyLink on setting up the new billing structure.

2 EBC Enterprise LAN upgrades K.Quire  
3 Design and build the Canyons SD PoP and redundant circuits to all schools K.Quire  
4 Install 69 new Tellabs nodes
K.Quire We continue to work with CenturyLink to complete these installations. UEN is prepared to install new circuits as they are made available by the provider.
5 Panguitch CO MPLS Conversion K.Quire Eliminated  
6 Complete Virtual Route Forwarding project K.Quire
K.Dutt
 
7 Replace all 3750Gs as they are no longer supported by Cisco
T.Jessup 85% Deferred to FY 2016

Pending staffing resources to complete these replacements.

8 Design and implement the Level-3 CoLo move. B.Bryson
K.Quire
Eliminated  
9 Complete Daggett County microwave Upgrade J.Egly
D.Sampson
 
10 Support Four Corners Network Development Project.
J.Egly Duplicate of #13  
11 Complete IVC Refresh engineering, design, project planning, and implementation based on UEN 2014/15 replacement funding (TBD) J.Egly 60% Deferred to FY 2016

IVC Replacement - RUS and STEM - 90% of the equipment procurement is complete and classroom installation is well underway. All STEM IVC rooms in northern Utah are scheduled for completion by the start of school. RUS room installation will continue into the fall.

UEN’s new RUS collaborative video bridging solution is installed and provisioning is underway. Testing and training will be conducted during the summer with the intent of moving it into production this fall.

12 Complete Lake Powell School network upgrades. J.Egly We have included this circuit in the current RFP and believe that we will be able to upgrade the bandwidth to 100 mbps.
13 Support Four Corners Network Development Project.
J.Egly Ongoing Deferred to FY 2016

As part of E-rate Modernization UEN was invited to participate in an FCC panel discussion in May to discuss how this program can be leveraged to benefit the Four Corners project.

UEN intends to leverage funding opportunities available through E-rate Modernization and bid fiber based services within the Utah portion of the Four Corners regions this year.

14 Continue to identify and evaluate emerging / next gen synchronous video solutions based on UEN and stakeholder requirements J.Egly
D.Maw
Ongoing Deferred to FY 2016

As part of its RUS project UEN will utilize a next generation collaborative video solution that can connect IVC classrooms and individual learners.

UEN also intends to pilot and utilize Cisco Collaborative Meeting Rooms (CMR) a cloud based solution that can bridge traditional IVC classrooms and individuals via WebEx.

15 Redesign and Bid All Alpine Elementary Schools.
K.Dutt 90% Deferred to FY 2016

The bid process is 100% complete, however, we are still waiting for funding to Implement.

16 Complete USHE/Snow College/Sevier School District IVC Pilot D.Litster
D.Mahaffey
 
17 Complete two new Snow College IVC classroom installations. D.Litster
D.Mahaffey
 
18 Snow College PoP Redesign and upgrade K.Dutt Completed Sept. 2014
19 South Sanpete Network Redesign and Upgrade ­ K.Dutt Completed Oct. 2014
20 North Sanpete Network Redesign and Upgrade K.Dutt Completed Nov. 2014
21 Upgrade Washington District primary connection to DSC to 10Gig K.Dutt Completed Sept. 2014
22 Alpine District 10 Gig upgrade to DDC K.Dutt Completed Mar. 2015
23 San Juan District ­ Fiber improvements to LaSal Elementary, Monticello HS, and Monticello Elementary K.Dutt Completed Jan. 2015
24 UVU Capitol Reef Field Station ­ Microwave K.Dutt Completed Jan. 2015
25 Continue IT Asset Management Project J.Stewart
B.Peterson
75% Deferred to FY 2016

Commissioned and completed a techical analysis of the FileMaker Database, received a report with recommendations, determined that this database is technically sound. Continued to refine data and processes around asset management. Weekly meetings to review goals and progress continue. Next step to accommodate TSSC’s asset management needs.

26 Replace one Microwave TX/RX pair as part of an ongoing Statewide Distribution Microwave Backbone infrastructure replacement plan. P.Titus  
27 SANS 20 Critical Control evaluation / risk assessment T.Jessup Completed Jan. 5, 2015
28 10 Gb Washington District ( Hurricane to Washington DDC). K.Dutt 80% Deferred to FY 2016

Waiting for equipment and infrastructure completion

29 Washington District additional capacity K.Dutt 65% Deferred to FY 2016

30 10 Gb backbone Price to San Juan. K.Dutt 85% Deferred to FY 2016

This will be complete End of July

31 CiB Grant: New Ethernet Radio Install San Juan, Monument Valley, Montezuma Creek, Navajo Mtn. K.Dutt 90% Deferred to FY 2016

32 RUS Grant: 48 IVC Rooms K.Dutt 40% Deferred to FY 2016

Recived equipment, implementation in process

33 STEM: IVC rooms Cache District K.Dutt 80% Deferred to FY 2016

34 San Juan Hub Move/Fiber and Network K.Dutt 65% Deferred to FY 2016

Hub move scheduled mid July.

35 10Gb UVU to UVW K.Dutt 60% Deferred to FY 2016

36 10 Gb Nebo District K.Dutt 80% Deferred to FY 2016

Waiting for equipment

37 10Gb Provo District K.Dutt 80% Deferred to FY 2016

Waiting for equipment

38 Add 3 Utah Radiology locations (Provo, Orem, St. George) to UTN network M.Cesarini Expand bandwidth in FY 2016
39 Add 4 community health centers (3 in Cache Valley; 1 in Evanston WY) to UTN network M.Cesarini