Network Services Application Services
Support Services
Operational Services
Network Services | Lead | % Complete | Status Report as of 7/15/2013 | |
1 | ![]() |
J.Stewart S.Corbató |
90% | USU, Salt Palace, 100 GigE turn up remaining |
2 | ![]() |
J.Brown J.Stewart J.Egly |
98% | Original project scope is 98% complete. NTIA approved grant deadline extension to May 31, 2013 which includes additional infrastructure hardware and fiber IRUs. |
3 | ![]() |
J.Stewart L.Hunter |
![]() |
Completed Nov. 2012 |
4 | ![]() |
J.Egly | ![]() |
All optical network components in place and in operation and ready to terminate to stakeholder layer 2/3 network devices. |
5 | ![]() |
J.Brown K.Dutt |
85% | This status pertains to all UEN awarded head start and elementary schools. |
6 | ![]() |
J.Brown | 5% | This project is pending E-rate funding. UEN is currently completing planning activities. |
7 | ![]() |
L.Valles |
![]() |
This work is complete. |
8 | ![]() |
K.Dutt | ![]() |
Completed August 2012 |
9 | ![]() |
J.Stewart | 75% | Meetings were held throughout the last 4 months of 2012. Needed data was collected, a report format was agreed upon and writing assignments were made. The report elements are in being written and in February and March, 2013, these report elements will be consolidated and presented in a first draft. The team, comprised of University of Utah and UEN staff, will revise and finish the report and then determine next steps. |
10 | ![]() |
J.Stewart K.Quire |
![]() |
Completed August 2012 |
11 | ![]() |
J.Stewart B.Bryson |
![]() |
UEN has completed the work necessary to provide this servcie. UMontana has not yet begun to use the service and is working out some technical details. University of Utah and UEN are working together to finalize contracts with IRON and UMontana. |
12 | ![]() |
T.Jessup | ![]() |
Working on finalizing the visualization systems during the week of January 21. Everything should be complete by February 1, 2013. |
13 | ![]() |
K.Krier J.Wong |
![]() |
Completed Sept 30, 2012 |
14 | ![]() |
L.Kuhn D.Sampson B.Bryson |
![]() |
Evaluations and awards completed on 1-24. New contract negotiations underway. |
15 | ![]() |
J.Stewart | 30% | Reviewing RFI proposals. |
16 | ![]() |
P.Titus | ![]() |
Equipment ordered, received and installed. |
17 | ![]() |
J. Egly K.Dutt |
![]() |
|
18 | Level3 router upgrades | K.Quire | 10% | Developing configs |
19 | EBC Enterprise LAN upgrades | K.Quire | 10% | Firewalls on order |
20 | Panguitch CO MPLS Conversion | K.Quire | 10% | In planning stages |
21 | Internet Border Router Replacement | K.Quire | 0% | Waiting for funding |
Application Services | Lead | % Complete | Status Report as of 7/19/2013 | |
22 | ![]() |
K.Branson K.Krier |
65% Deferred to FY14 |
The interface that aligners use to submit their alignment is back online. |
23 | ![]() |
B.Peterson | 45% Deferred to FY14 |
All new development is against PostgreSQL and many major services have moved to PostgreSQL. Mostly Sybase Databases left to move to PostgreSQL |
24 | ![]() |
B.Peterson | 40% Deferred to FY14 |
All Development, Preview, Release Candidate, and Production environments for www.uen.org are operational and will be in production in August 2013. |
25 | ![]() |
K.Garrett | ![]() |
Informational website and video were created and posted online: uen.org/legislature |
26 | ![]() |
K.Krier | ![]() |
Plan to launch in Aug. 2013. |
27 | ![]() |
B.Peterson | 20% Deferred to FY14 |
Allocated some small hardware resources. No longer waiting on collaboration time with Higher Ed. IT Staff. Higher Ed. asked UEN to not be involved. Will move to private cloud operationally for internal stuff and current hosted services. |
28 | ![]() |
K.Branson K.Krier |
Ongoing | The Documents Manager and message portlets were revised to allow educators to easily add images to their my.uen pages. The Services / Tools portlet now provides access to the UIMC+ eMedia for educators in UIMC districts / school. |
29 | ![]() |
L.Kuhn | Ongoing | On schedule; Adobe, Canvas, filtering, Pioneer, UIMC Complete |
30 | ![]() |
L.Hunter | ![]() |
FY12 licensing complete, FY13 billing complete, evaluations on schedule.; FY14 buy complete. |
31 | ![]() |
K.Branson K.Krier |
5% Deferred to FY14 |
|
32 | ![]() |
K.Krier | ![]() |
Decision not to pursue. |
33 | ![]() |
K.Garrett | ![]() |
Equella/Canvas integration completed in March 2013. |
34 | ![]() |
B.Peterson | 95% Deferred to FY14 |
All Data Spirals from initial load through spiral 3 are available in staging and production environments. Data quality evaluations completed through Spiral 2 and are in progress on spiral 3. |
35 | ![]() |
S.Allen J.Egly |
Ongoing | Pilot-testing SeeVogh with UU continues; Canvas Net+ service validation phase is about 95% complete. |
36 | ![]() |
J.Egly | 90% | Pending response from DTS regarding how they want to proceed with new UEN proposal for UEN IVC services. |
37 | ![]() |
K.Quire K. Dutt |
50% | Project is currently focused on improvements with USU and the U of U. |
38 | ![]() |
K.Branson | ![]() |
Complete |
39 | ![]() |
J.Stewart T.Jessup B.Bryson |
![]() |
Filtering RFP currently out, and expected to be completed by the end of January. iBoss deployment underway. |
40 | Explore consortium licensing for NBC Learn | L.Hunter | ![]() |
Decision not to pursue. |
41 | ![]() |
J.Egly | 15% Deferred FY14 |
Underway |
42 | ![]() |
J.Egly | 10% Deferred FY14 |
Dennis Sampson and Jeff Egly are assembling network design and grant detail to apply for CIB grant in October '13. Microwave costs assembled. Still required is the Ancillary DC and AC power requirements, and layer 2/3 network design and network hardware requirements. |
43 | ![]() |
L.Hunter | 33% | Initial planning and development stages. Mou complete; on schedule. |
44 | ![]() |
B.Peterson | 75% Deferred to FY14 |
DDC POP is online. Enterprise Networking Gear installed and initial configuration. Inter device physical connections in place. Layer 2 Ethernet and Fiber Channel connection between EBC and DDC are physically patched and need testing. Server and Rack networking Gear installed and connected. NAS Storage installed. |
Support Services | Lead | % Complete | Status Report as of 7/11/2013 | |
45 | ![]() |
R. Bentley | ![]() |
10 sections offered. |
46 | ![]() |
L.Hunter | ![]() |
Completed Nov. 2012 Added 4 Intel courses, Teaching and Learning with iPads, eBooks and eReaders in the Classroom, Teach Online with Canvas CMS, Utah Core Curriculum Resources and Projects, Canvas LMS: Deliver Instruction Online. |
47 | ![]() |
M.Hintze | ![]() |
3 courses developed and completed, starts January 17 |
48 | ![]() |
L.Hunter | ![]() |
18 guides published. |
49 | ![]() |
L.Hunter L.Cohne |
Ongoing | Education-engagement projects on track as described in NSF proposals |
50 | ![]() |
D.Jones | Ongoing | Courses developed and deployed, undergoing course revision and improvements based on pilot semester. |
51 | ![]() |
R.Cline | 85% | CIPA compliance letter sent to superintendent's and principals; NetSafe trainers responding to presentation requests. |
52 | ![]() |
K.Garrett | ![]() |
Supporting ongoing projects as needed |
53 | ![]() |
L.Hunter K.Krier |
![]() |
Website, videos complete; additional support as requested. Hosted NROC webinars to aid in course development. Steering Cmte and workgroup support ongoing |
54 | ![]() |
D.Mahaffey | 99.5% | 50 new IVC classroom have been installed and 28 IVC classroom have been moved or upgraded. The last classroom installation has been started. The room is waiting for desks to be setup before the IVC installation can be completed. |
55 | ![]() |
T.Jessup | ![]() |
Three institutions are complete, Continuing process for the remaining. |
56 | ![]() |
J.Stewart | ![]() |
Conferences FY13 complete. |
57 | ![]() |
L.Cohne | ![]() |
Complete. As of 12/1/12, five film screenings took place at museums, libraries and higher ed. institutions with over 200 participants highlighting American Indian Heritage Month. |
58 | ![]() |
L.Hunter K.Krier K.Garrett |
![]() |
Completed Nov. 6, 2012 - ed website, PR to journalism departments, promoted in a variety of ways, supported debatee video and audio files in eMedia |
59 | ![]() |
L.Hunter J.Gibbs |
![]() |
Met FY13 goals; on schedule. |
60 | ![]() |
L.Hunter | ![]() |
Meetings in Dec 2012, partnership outlined and in progress with USBE; contract complete. |
61 | ![]() |
R.Cline | 50% Deferred FY14 |
Consensus to Defer until FY14. |
62 | ![]() |
R. Bentley | 0% | |
63 | ![]() |
R. Finlinson | ![]() |
Completed March 2013. |
64 | Implement NROC Webinars and Training | K.Garrett | ![]() |
Converted NROC courses to Canvas IMSCC format. As new content is released from NROC, we will add it to eMedia. Additional trainings and webinars will be scheduled as needed. |
65 | Research online Ed Tech Endorsement program | L.Hunter | 10% Deferred FY14 |
Initial meetings with SUU, SEDC, and others |
66 | Design FY14 Training program for web conferencing | J.Brooksby | 0% Deferred FY14 |
Pending RFP award. |
Operational Services | Lead | % Complete | Status Report as of 7/19/2013 | |
67 | Hire new Executive Director | E.Denna | ![]() |
Complete September 2012 |
68 | ![]() |
L.Hunter | ![]() |
Complete October 2012 |
69 | ![]() |
R. Timothy | ![]() |
Meeting held in February and meeting planned for April. |
70 | ![]() |
L.Hunter | ![]() |
Diversity Guidelines Approved, website updates in progress. |
71 | ![]() |
J.Stewart | 90% Deferred FY14 |
Database development complete, inventory of red and yellow stickered items complete, Altiris development database created, Altiris production database development underway, data entered and cleanup ongoing, data provided from accounting regarding purchase dates and costs. Currently staff is reconciling accounting data and adding data regarding equipment end-of-life dates and replacement costs. Database will be used for acquisition, moves and retirement of all equipment purchased by UEN. Technical staff has been trained on the new system and process. Further training for all UEN staff will be required once the production database will be scheduled. |
72 | Develop capital equipment refresh budget & Board | L.Kuhn | ![]() |
Completed August 2012 |
73 | ![]() |
R.Finlinson | ![]() |
Completed April 2013 |
74 | ![]() |
R. Timothy | 50% | Continued refinement. |
75 | Prepare service-aligned budget | L.Kuhn | ![]() |
Completed December 2012 |
76 | ![]() |
V. Rasmussen | 75% Deferred FY14 |
|
77 | ![]() |
J.Stewart L. Hunter E. Hacker |
![]() |
Dependency model was developed by leadership team and presented at the February board meeting. |
78 | Produce Legislative Ask website, videos, materials | L. Hunter K. Krier K. Garrett |
![]() |
Complete: uen.org/legislature |
79 | Implement BoardDocs | L. Hunter | ![]() |
Implemented in March. |